Heat Pump Electrical Supply Upgrade UK 2026
Heat pump electrical supply upgrade UK 2026: DNO G98/G99 consent, fuse upgrades, 3-phase considerations, realistic GBP 200-1500 cost ranges.

A heat pump adds roughly 4-7 kW of continuous electrical load to your home - similar to running an electric oven non-stop. Most UK domestic supplies can handle it, but some need formal upgrade work + DNO consent. This guide covers what the supply assessment involves, when upgrades are needed, and the realistic 2026 UK cost ranges.
G98 + G99: the consent regime
Engineering Recommendation rules governing low-voltage generator + load connections.
UK Distribution Network Operators (DNOs) require notification or consent before any significant load is connected to the grid, under Energy Networks Association Engineering Recommendation G99 (and its smaller-load sibling G98):
- G98 notification - covers heat pumps drawing under 16A per phase (most UK 5-8 kW domestic units). The installer files the notification with your DNO after install; processing is typically 2-5 business days. No pre-install consent required.
- G99 application - covers heat pumps over 16A per phase OR any 3-phase install. The installer submits the application pre-install; DNO assessment + approval typically 2-4 weeks. Larger heat pumps (10kW+), ground-source installs, and properties needing supply upgrade all fall here.
For typical UK 3-bed semi installs (5-8 kW air-source heat pump on single-phase 100A supply), G98 notification applies + the timeline is post-install paperwork only - no delay to install scheduling.
Existing supply assessment
Three measurements that determine whether upgrade is needed.
Your installer assesses three things during the MCS heat loss survey:
- Main service fuse rating. Typically printed on the cut-out (the sealed unit where the service cable enters the property). Common UK ratings: 60A, 80A, 100A. Heat pumps need at least 60A + comfortable headroom; 80A or 100A is the safe baseline.
- Existing electrical load. EV charger (7-22A continuous), electric shower (35A peak), induction hob (32A peak), heat pump (16-32A continuous). The DNO calculates 'maximum demand' based on the household's load profile.
- Service cable size + condition. Older properties may have small or aged service cables (typically 25mm² or smaller) that can't carry the full fuse rating. Visible from the cut-out + the meter cabinet.
Most properties built post-1990 have 100A single-phase + adequate cable. Pre-1990 urban properties + rural properties with long supply cables may need investigation.
Realistic UK 2026 upgrade costs
Four scenarios from no-upgrade to full 3-phase conversion.
Scenario 1: No upgrade needed (most common).
- Existing 80A or 100A fuse, modern service cable, room for additional load.
- G98 notification only.
- Total cost: GBP 0 beyond the heat pump install itself.
Scenario 2: Fuse upgrade only (common for pre-1990 properties).
- Service cable rated for 80A+ but main fuse is 60A.
- DNO replaces the cut-out fuse with an 80A or 100A version.
- Typical cost: GBP 200-400, processed via G99 with 2-4 week consent.
Scenario 3: Service cable upgrade (older terraced properties).
- Existing service cable too small for 80A+ load (25mm² or smaller).
- DNO replaces cable from cut-out to street feed (often requires road excavation).
- Typical cost: GBP 800-1,500, 3-6 week timeline including street work.
Scenario 4: 3-phase conversion (large properties + heavy load).
- Property has high combined load (heat pump + EV + induction cooking + electric shower + workshop).
- DNO converts single-phase to 3-phase supply.
- Typical cost: GBP 2,500-8,000, 6-12 week timeline. Sometimes more if street excavation is extensive.
For typical UK 3-bed semi installs in scenarios 1 + 2, electrical upgrade is either zero cost or a manageable fraction of the heat pump install. Scenario 3 cases need budgeting for; scenario 4 cases need pre-install consultation with the DNO to confirm timeline + cost.
Who handles the DNO paperwork
Reputable installers do this for you - confirm before signing.
Standard practice across UK heat pump installers:
- BOXT, Octopus Energy, Aira, British Gas, Vaillant Advance partners, Mitsubishi MELCloud installers - all handle G98 notification + G99 application as part of the install package. Quote should include this.
- Smaller independents - typically handle it but check explicitly in the quote. Some pass DNO fees through (~GBP 150-300 for G99 application processing).
- DIY-route or substandard installers - leave the DNO consent to the customer. Avoid this - DNO paperwork errors can void the heat pump warranty + cause grid-side issues.
What you need to provide: existing fuse rating (visible on the cut-out), current household electrical load profile (existing high-load appliances), and the planned heat pump model + kW rating.
Timeline impact
When DNO consent delays the install schedule.
For most installs (Scenario 1 + 2), DNO consent runs parallel to install scheduling - no impact on the timeline. For Scenarios 3 + 4:
- Service cable upgrade (Scenario 3): 3-6 weeks added to install timeline. The DNO schedules the cable upgrade independently of the heat pump install date.
- 3-phase conversion (Scenario 4): 6-12 weeks added. Often requires street excavation + can include road-closure permits + reinstatement work.
Plan around this if your install date is time-critical (e.g. before next winter). The good news: most UK installs land in Scenarios 1 + 2 + don't see delays from electrical work.