What Happens at Heat Pump Commissioning? UK 2026 Checklist
Heat pump commissioning checklist for UK homes: the numbers to record, the handover pack, when the MCS certificate arrives and how it unlocks BUS.

Most commissioning checklists list what the engineer does. This one is about what you walk away with: the figures and documents that every later conversation about your heat pump depends on. Your first-winter bill check, a warranty claim and a house sale all go back to what was written down on this one day.
Commissioning normally lands on the last day of a four-to-five-day install. Planning the install itself is covered in our installation timeline guide, and the questions to ask before you sign a quote are in what to ask a heat pump installer. This guide picks up when the outdoor unit is in, the pipework is done, and the engineer is ready to set the system to work.
What does heat pump commissioning actually prove?
Three things: it is safe, it matches the design, and it is documented.
Commissioning is the installer's check that the system as built matches the system as designed. The design comes from the room-by-room heat loss calculation (covered in our heat loss survey guide); commissioning is where the design flow temperature, the emitter sizes and the cylinder choice meet reality.
Under MCS (the Microgeneration Certification Scheme, the UK's certification body for small renewable installations), the heat pump standard is split into a design document, MIS 3005-D, and an installation document, MIS 3005-I, which covers setting the system to work. Many installers also complete a Benchmark commissioning checklist, the heating industry's standard record, which since late 2023 feeds into MCS registration so the data is entered once.
For you as the homeowner, the practical upshot is simple. Anything not written down on commissioning day is hard to prove later. The checks below are grouped by what they leave on paper.
Check 1: Has the system been filled, pressure-tested and dosed?
The first entries on the commissioning record.
Before the heat pump runs, the engineer fills the heating circuit, adds corrosion inhibitor (and antifreeze or anti-freeze valves on the outdoor pipework, depending on the design), bleeds every radiator and pressure-tests the system.
- Ask what test pressure and hold time were used, and that the result is written on the commissioning record.
- Ask which inhibitor went in and how the concentration was checked. A test strip or meter reading on the record is better than a verbal assurance.
- Look for drips at the outdoor unit connections, the cylinder and any new valves before the walls and floors are made good.
This is also when the engineer confirms the system holds enough water for the heat pump to defrost and run without short cycling. A homeowner handover checklist that asks for confirmation of minimum water volume is a reasonable request; the manufacturer's installation manual states the figure for your model.
Check 2: Is the design flow temperature set, and does the house heat?
The single most important number for your running costs.
On the first proper run the outdoor unit should start cleanly, the controller should show no fault codes, and every radiator or underfloor zone should warm up. The engineer should then show you two numbers on the controller:
- Design flow temperature. The water temperature the system was sized to deliver on the coldest design day. Radiator systems designed for a heat pump usually sit between 45°C and 55°C, underfloor heating lower. It should match the figure in your heat loss design.
- Flow and return temperatures right now. The gap between them (the delta T) tells you water is circulating properly. Ask what delta T the design assumed.
If the design flow temperature on the controller is higher than the one in the quote paperwork, ask why before the engineer leaves. A system running hotter than designed costs more every day it runs.
Check 3: How is the weather compensation curve set?
Commissioning sets the starting point; tuning comes later.
Weather compensation adjusts the flow temperature automatically as the outside temperature changes. The Energy Saving Trust's installer guidance on weather compensation notes that the outdoor sensor is either built into the outdoor unit or fitted outside, normally on a north-facing wall, and that most homes respond well to a minimum flow temperature of 20-25°C, subject to the manufacturer's own limits.
At commissioning, ask the engineer to show you:
- Where the curve lives on the controller, and the two ends of it: the flow temperature at the design outdoor temperature and at mild weather.
- The minimum flow temperature they set, and why.
- Whether any room thermostat is set to override the curve, and how.
Write the settings down or photograph the screen. Fine-tuning the curve over the first few weeks is a separate job; our weather compensation curve setup guide walks through it, and it needs these starting values.
Check 4: Does the hot water cylinder reheat in a sensible time?
A quick arithmetic check you can do yourself.
The engineer should run a cylinder reheat in hot-water mode and note the time. You can sanity-check the result with basic physics. Heating 200 litres of water from 15°C to 55°C takes about 9.3 kWh of heat. A 7 kW heat pump delivering its full output into the cylinder would need roughly 80 minutes, plus some allowance for losses and for the cylinder coil limiting how fast heat transfers.
So a reheat of around 80-100 minutes for that pairing is in the right range. A reheat of well over two hours points to a cylinder coil that is too small for the heat pump, a flow-rate problem, or a control setting holding output back. Raise it on the day, while the engineer can still look.
Check 5: What operating data goes on the record?
A snapshot you will compare against in your first winter.
Older checklists ask for a COP (coefficient of performance) figure at commissioning. Treat a single spot COP with caution: it depends on the outdoor temperature and flow temperature at that moment, and many domestic systems have no heat meter to measure output accurately. A commissioning-day COP is not your seasonal efficiency. The difference is explained in our COP vs SCOP guide.
What is worth recording is the raw operating data, because it is comparable later:
- Date, time and outdoor temperature
- The conditions every other reading depends on
- Flow and return temperatures
- Read from the controller during a steady run
- System flow rate
- From the controller or a flow meter, if fitted
- Electrical input
- From the controller, app or a dedicated meter, if fitted
- Design flow temperature and curve settings
- The figures from Checks 2 and 3
- System pressure (cold)
- So you know what normal looks like on the gauge
- Heat pump model and serial number
- Needed for warranty registration and any claim
Keep this table with your paperwork. When you compare your first bills against the installer's estimate, as set out in our first-winter guide, these numbers tell you whether the system is still running as commissioned.
Check 6: Are the controls and tariff set up for how you live?
Factory defaults are rarely right for a household.
Ask the engineer to set room temperatures, hot water times and holiday mode with you at the controller, not for you. If your quote included smart-tariff setup, for example with Octopus Energy's Cosy Octopus heat pump tariff, confirm that the heat pump schedule actually uses the cheap windows for hot water and any pre-heating. Where the manufacturer's app (MELCloud, myVAILLANT, ViCare and similar) is part of the package, check it shows live data on your phone before the engineer leaves.
Smart integration is the step most often left as "you can sort that later". If it was in the quote, it belongs on the commissioning day.
Check 7: Is the warranty registered and the first service booked?
Two conditions that protect you for years.
Manufacturer warranties on heat pumps commonly run from five to ten years, but the longer terms usually depend on the unit being registered, often within a set period of installation, and on annual servicing. Ask the engineer to register the serial number on the day, or to confirm in writing when they will, and ask for the confirmation email to be forwarded to you.
- Check the warranty start date matches the commissioning date.
- Ask whether the first annual service is included, and get the cost of later services in writing.
- Book the first service now, roughly 12 months out.
If you ever need to use the warranty, our warranty claims and disputes guide explains how the installer and manufacturer layers fit together.
When does the MCS certificate arrive, and why does it matter?
It is generated after commissioning, not signed on the day.
A common misunderstanding is that the homeowner signs an MCS certificate on commissioning day. The certificate is generated when the installer registers the installation on the MCS Installation Database (the MID, the central register of certified installations). GOV.UK guidance says that if you used an MCS certified installer, you should get your MCS certificate within 10 days of completion.
Some installer-side summaries of MCS's redeveloped scheme describe a longer window for raising the certificate. In practice: if it has not arrived within 10 days, ask for it in writing. You can look up the installation on the MCS certificate checker once it is registered.
The certificate matters well beyond warranty. It records what was installed and is the document a buyer's solicitor asks for when you sell. It also unlocks the grant.
How does commissioning connect to your BUS grant?
The installer redeems the voucher, after commissioning and certification.
Under the Boiler Upgrade Scheme (BUS, the England and Wales grant worth £7,500 for most air source heat pump installs), the grant is paid to the installer, not to you. Ofgem's guidance for installers sets the order: the installer commissions the system and generates the MCS installation certificate, then applies to redeem the voucher, and Ofgem checks the certificate's details before paying. The same guidance gives installers three months from the voucher's issue date to complete the installation, or six months for a ground source heat pump.
You consent to the application at the start, when Ofgem emails you; there is no homeowner signature at redemption. Two things follow for you:
- Your final invoice should already show the grant deducted. If an installer asks you to pay the full price and wait for the grant, query it.
- Ofgem only accepts BUS applications from installers certified under MCS for the technology they fit, so check certification before work starts. Our guide to vetting an MCS installer covers how.
The step-by-step grant process is in our BUS application guide.
What should be in your handover pack?
The document checklist to tick before the engineer leaves.
Commissioning record
The completed commissioning checklist (Benchmark or the installer's own), with pressure test, inhibitor, flow temperatures and the operating data from Check 5.
Heat loss calculation and design
The room-by-room heat loss figures, the design flow temperature and the emitter schedule the system was built to.
Product details
Make, model, kW output and serial number of the heat pump and cylinder, plus the user manuals.
Warranty registration
Confirmation from the manufacturer, or a written date by which the installer will register it.
Service arrangement
First service date, what it costs, and who to call for faults in the first weeks.
MCS certificate (to follow)
Expected within 10 days of completion per GOV.UK; chase it in writing if it is late.
Hold back final sign-off on the installer's own paperwork until the items you can check on the day are complete. Your consumer rights under the Consumer Rights Act 2015 do not disappear when you sign a handover form, but a clear record of what was and was not done makes any later dispute much simpler.
Before the engineer leaves: what should you ask?
Use the last half hour well.
- Which fault codes can I reset myself, and which need a call-out?
- What clearance does the outdoor unit need, and what do I do about leaves or snow?
- What does defrost look and sound like, so I don't mistake it for a fault?
- How long should hot water take to recover after a bath or shower?
- Who do I call in the first 30 days, and what is the manufacturer's support line after that?
Write the answers down. The first cold week raises plenty of small questions, and our FAQs for new heat pump owners answer the common ones.
The short version
Commissioning is about evidence, not ceremony.
Commissioning day is your one chance to capture how the system ran when it was new. Get the design flow temperature, the curve settings, the operating snapshot and the warranty registration on paper before the engineer goes. Then chase the MCS certificate within 10 days, because your installer needs it to redeem the grant and you need it for the life of the system.
What should be on a heat pump commissioning checklist?
Do I sign the MCS certificate on commissioning day?
When is the Boiler Upgrade Scheme grant paid?
What COP should my heat pump show at commissioning?
What if my MCS certificate does not arrive?

Heat pump installation timeline

Weather compensation curve setup

Your heat pump's first winter
